By Catherine Zhou
Oct. 15 2021
I think most of you have heard about the energy crisis all over the world.
In order to face the crisis, we Chinese factories have been asked to recude work time so as to save energy.
We have been informed by many of our material suppliers that they will work 4 days and stop for 3 days a week from now on. Some evern work 2 days and stop for 5 days a week.
So, in the near furture, the leading time of our suppliers will be longer than before and result in the longer leading time of our products.
Usually our leading time is 30-45 days, but in the near future, the leading time might be 45-60 days if there’s no stock in our warehouse. This situation will exist until the energy crisis is alleviated.
We do suggest our customers to prepare for orders much ealier than previous. But we will also keep some stock to make sure our customers will not wait too long.
Please feel free to contact me if you are interested in our products.